Procedures for changing land use purposes to implement projects is a process that directly affects the rights and obligations of investors. Understanding procedures, documents and related conditions helps customers carry out the project smoothly. This article provides detailed information about procedures for changing land use purposes to implement projects, to help customers clearly understand the process and ensure their rights.

Table of Contents
ToggleLand Law 2024 clearly regulates conditions for changing land use purposes for each type of investment project. Specifically, according to Clause 2, Article 122 of the Land Law 2024, investors need to meet the following conditions:
For commercial housing construction investment projects, Clause 3, Article 122 of the Land Law 2024, additional conditions need to be met:
These conditions are to ensure that investment projects are implemented transparently, effectively, and in accordance with local development planning.
>>> See more: Capital Contribution by Land Use Rights – Conditions and Procedures.
Pursuant to Article 227 of the Land Law 2024 and Article 44 of Decree 102/2024/ND-CP, procedures for changing land use purposes to implement project as follows:
To carry out the procedure for converting land use purpose, the following documents need to be fully prepared:
The procedure includes the following steps:
Step 1: Submit application
The land user submits 01 application to change the land use purpose to the One-Stop Department of the Provincial People’s Committee.
The agency with land management function assigns the Land Registration Office to perform the following tasks:
Step 2: Processing documents
The agency with land management function completes the dossier and submits it to the competent People’s Committee to issue a decision allowing the change of land use purpose.
Documents submitted to the People’s Committee include:
After receiving the dossier from the agency with land management functions, the competent People’s Committee shall consider and issue a decision allowing the change of land use purpose.
Receiving the decision allowing change of land use purpose from the competent People’s Committee, the agency with land management function transfers the cadastral information of the land plot to the tax authority.
Tax authorities determine land use fees and land rent payable according to regulations. Then, issue a notice of payment of land use fees and land rent to the land user.
Step 3: Pay land use fee
Step 4: Complete the procedure and receive results
Processing time: no more than 20 days. For mountainous communes, islands, remote areas, areas with difficult socio-economic conditions, areas with particularly difficult socio-economic conditions, the implementation time is increased by 10 working days.
Above are detailed procedures for changing land use purposes to implement projects. Customers need to understand clearly to ensure that the process of changing land use purposes takes place smoothly and legally.
Pursuant to Clause 1, Article 7 of Decree 103/2024/ND-CP, land use fees when changing land use purposes to implement projects are calculated according to the following formula:
Land use fee when changing land use purpose = Land use fee for land type after changing land use purpose – Land use fee, land rent for land types within the scope of project implementation before changing land use purpose (if any).
In there:
Customers should pay attention to the calculation method to determine the exact amount of land use fees that they must pay when changing the land use purpose.
Long Phan Consulting Company provides professional consulting services on procedures for changing land use purposes, including:
With extensive experience and expertise, Long Phan Consulting Company is committed to supporting customers in carrying out procedures for changing land use purposes quickly, in accordance with regulations and ensuring the best benefits. We accompany throughout the process, from legal advice to completing procedures, helping customers save time and limit risks.

Below are frequently asked questions about procedures for changing land use purposes to implement projects, customers can refer to:
Processing time should not exceed 20 days. For mountainous communes, islands, remote areas, areas with difficult socio-economic conditions, areas with particularly difficult socio-economic conditions, the implementation time is increased by 10 working days.
The land registration office will guide you to supplement or redo your documents to resubmit.
Documents proving land use rights include land use rights certificates, land allocation decisions, land lease decisions, or other legal documents issued by competent state agencies.
The conversion must be consistent with land use planning and local socio-economic development plans and plans. Some special types of land may be restricted from conversion according to the provisions of law.
The field inspection process is carried out by the Land Registration Office to ensure the information in the records is accurate with the actual land use status.
Excerpt from the cadastral map of a land plot is a drawing showing the location, boundaries, and area of the land plot, necessary to accurately determine land information in the application for change of use purpose.
Yes, in case the land is in dispute, the procedure for changing the land use purpose will be suspended until the dispute is resolved according to a court ruling or decision of a competent state agency.

In order for the process of changing land use purposes to take place smoothly and legally, customers need to clearly understand the provisions of law, land use purpose change documents and other related documents. Long Phan Consulting Company is ready to assist customers in completing procedures quickly and effectively. When needing advice on procedures for changing land use purposes to implement projects, customers can contact the hotline: 0906735386 for support.









Note: The content of the articles published on the website of Long Phan Investment Consulting Company is for reference only regarding the application of legal policies. Depending on the time, subject, and amendments, supplements, and replacements of legal policies and legal documents, the consulting content may no longer be appropriate for the situation you are facing or need legal advice on. In case you need specific and in-depth advice according to each case or incident, please contact us through the methods below. With our enthusiasm and dedication, we believe that Long Phan will be a reliable solution provider for our clients.
Leave your email to receive the latest information from us
CONTACT: 1900.63.63.89
Copyright 2024 © Long Phan Consulting Company. All rights reserved.