A license to build individual houses is a mandatory document when individuals and households want to build housing projects in Ho Chi Minh City. Applying for a construction permit requires detailed procedures, from preparing documents to submitting applications at the competent authority. Through the article below, Long Phan will guide you step by step and provide the necessary information to apply for a license to build individual houses in accordance with the law.
According to the provisions of Article 93 of the Law on Construction 2014, individuals and households are only granted permits to build individual houses if they meet the following conditions:
Compatible with planning:
Ensuring project safety:
Valid documents:
To apply for permission to build individual houses, customers need to prepare the following documents:
1. Application for license: According to Model number 01 in Appendix II of Decree 15/2021/ND-CP.
2. Documents proving land use rights: Need one of the documents prescribed by land law.
3. Construction design drawings: Need 02 sets of drawings accompanied by a certificate of fire protection design approval (if required), including:
4. Design drawing sample: Provincial People’s Committees can publish sample drawings for households and individuals to refer to when making their own designs.
Documents must be fully prepared and according to the required form to ensure validity when submitted to the competent authority.
CSPL: Article 95 Law on Construction 2014, Article 46 Decree 15/2021/ND-CP.
The district-level People’s Committee is the agency responsible for issuing construction permits for individual housing projects in the area. The authority to grant permits belongs to the district People’s Committee where the construction project is located.
The process of applying for a license to build individual houses includes the following steps:
Step 1: Receive and check documents
Step 2: Document appraisal and field inspection
Step 3: Get opinions from relevant management agencies
Step 4: Issue construction permit
The total processing time for licensing applications can last up to more than 50 working days including preparation, submission and appraisal time.
CSPL: Article 102 Law on Construction 2014.
With a team of consultants with many years of experience, Long Phan provides professional and effective support services for applying for individual housing construction permits in Ho Chi Minh City, including:
With extensive knowledge of the Law on Construction and experience in handling complex administrative procedures, Long Phan is committed to providing customers with quick, effective consulting services, saving time and effort. For support, please contact Long Phan via hotline 0906735386. Ensure procedures are completed according to regulations and schedule, helping customers quickly deploy construction projects as planned.
Note: The content of the articles published on the website of Long Phan Investment Consulting Company is for reference only regarding the application of legal policies. Depending on the time, subject, and amendments, supplements, and replacements of legal policies and legal documents, the consulting content may no longer be appropriate for the situation you are facing or need legal advice on. In case you need specific and in-depth advice according to each case or incident, please contact us through the methods below. With our enthusiasm and dedication, we believe that Long Phan will be a reliable solution provider for our clients.
Leave your email to receive the latest information from us
CONTACT: 0906 735 386
Copyright 2024 © Tư vấn Đầu tư Long Phan. All rights reserved.